Requirements
1.
Letter of introduction (original)
given by the company to the person submitting the application file
2.
Statement for construction design evaluation (original)
Legal dossier, including:
1.
Decision on approval of investment project on the construction of work (original)
certified by investor (company) for case of two or three-step design
or
In-principle approval on construction of work (original)
certified by investor (company) for case of one-step design
2.
Conceptual design dossier approved together with investment project on construction of work (original)
3.
Certificate of fire prevention and fighting appraisal and approval (Simple copy)
and drawing dossier certified by company
Dossier showing capability of surveying constructor, including:
1.
Business registration certificate (an authentic copy)
of surveying constructor
2.
Practicing certificate (an authentic copy)
of surveying engineer leader
Dossier showing capability of consulting company making investment project on construction of work, including:
1.
Business registration certificate (an authentic copy)
of consulting company making investment project on construction of work
2.
Practicing certificate (an authentic copy)
of designing leaders
Planning dossier scale 1/500 approved by competent authority, including:
1.
Approved 1/500-scale detailed construction blueprint (Simple copy)
certified by company
or
Master plan and preliminary architectural plan approval (Simple copy)
certified by company
or
Documents on architectural planning information (Simple copy)
1.
Decision on EIA report approval (Simple copy)
(if any) certified by company
or
Environmental protection commitment (Simple copy)
certified by company (if any)
2.
Written agreement on functional State management (Simple copy)
certified by company: - dyke management (if any)
- security and national defense (if any)
- cultural or monument work protection (if any)
- high voltage grid (if any)
3.
Written agreement on techinical infrastructure connection (Simple copy)
certified by company - water supply (if any)
- water discharge (if any)
- power supply (if any)
Surveying and designing dossier, including:
1.
Design explanation (original)
(in compliance with Article 7.4 Circular 13/2013/TT-BXD)
2.
Design drawings (original)
3.
Construction survey dossier (original)
4.
Construction of work maintaining procedure and technical guide (original)
Time frame
Time limit for handling the application file: 20 working days for one-step design project and 30 working days for two or three-step design project as from the date of submitting application file.
Waiting time in queue:
Max. 10mn
Attention at counter:
Min. 5mn - Max. 30mn
Waiting time until next step:
Min. 20 days - Max. 30 days
Legal justification
1.
Law No. 50/2014/QD13 dated 18/06/2014 of the National Assembly on Construction
articles 82, 83
2.
Decree No. 15/2013/ND-CP of the Government dated February 6, 2013, on quality management of construction works
articles 6, 20, 21
3.
Circular No. 13/2013/TT-BXD of the Ministry of Construction dated August 15, 2013, prescribing verification, appraisal and approval for works construction design
articles 3, 4, 5, 7, 8
4.
Circular No. 10/2013/TT-BXD of the Ministry of Construction dated July 25, 2013 on construction quality management
Article 7
5.
Decision No. 56/2013/QD-UBND of Hanoi People's Committee dated Dec 11, 2103 prescribing verification, appraisal and approval for works construction design in Hanoi
articles 9, 10, 11
6.
Official Letter No. 3482/BXD-HDXD of the Ministry of Construction dated Dec 30, 2014 on implementation of Law No. 50/2014/QH13 on Construction
Article IV
7.
Official Letter No. 254/BXD-HDXD of the Ministry of Construction dated Dec 30, 2014 guiding some content of design appraisal in accordance with Law No. 50/2014/QH13 on Construction
Article 5