Meet HAPI
Define location  (1)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Propose to take project into the list of projects for investor selection  (1)
Obtain document on investor appointment  (2)
Obtain authenticated copies of document on investor appointment  (2)
Obtain agreement on location plan  (2)
Obtain current condition land map  (1)
Define red line boundaries and technical indications  (3)
Obtain construction planning certificate (or planning information)  (2)
Obtain planning license  (2)
Obtain master plan and and preliminary architectural plan approval  (2)
Obtain 1/500-scale detailed construction-planning tasks appraisal and approval  (2)
Obtain 1/500-scale detailed construction-planning blueprints approval  (2)
Obtain information on land use plan  (2)
Obtain Investment Certificate  (3)
Receive evaluation document on land use demand, conditions for land lease, land assignement  (1)
Obtain authenticated copies of Investment Certificate  (2)
Make seal and notify seal specimen  (3)
40
Make seal
Obtain certificate of tax registration  (2)
Open bank account  (1)
Publish in newspaper  (1)
Prepare construction investment project  (1)
Obtain approval on environmental impact assessment  (3)
Prepare construction dossier (including: fire fighting design dossier)  (1)
Obtain fire prevention and fighting appraisal and approval (for conceptual design dossier)  (2)
Obtain opinions on conceptual design  (2)
Obtain land lease decision  (2)
Receive notification on land rental amount (for land plot value of less than 30 billion Dongs)  (1)
Sign land lease contract  (3)
Pay land rental  (1)
Make landmarks definition plan for extracted map of land plot  (3)
Receive land plot on site and obtain extracted map of land plot  (4)
Obtain land use rightcertificate  (5)
Obtain fire prevention and fighting approval  (2)
Request for construction design evaluation (for a number of construction work as provided by law)  (2)
Obtain construction permit  (2)

Preview & Print

Properties
 
16
Submit application for agreement on location plan
(last modified: 6/28/2015)

Timeframe ( ver detalles )

Espera hasta paso siguiente

5 mn  -  40 mn
0 days  -  5 days

Contact details

Entity in charge

Hanoi Authority for Urban Planning & Architecture

31b Trang Thi Street, Hoan Kiem District , Hanoi
Tel: +84 4 3823 2313/+84 4 3823 2312
Fax: +84 4 3823 0074
Email: support@qhkt.gov.vn
Website: http://qhkthn.gov.vn/

Unit in charge

Reception & Release Desk

Mon: 08:00-11:30, 13:30-16:30
Tue: 08:00-11:30, 13:30-16:30
Wed: 08:00-11:30, 13:30-16:30
Thu: 08:00-11:30, 13:30-16:30
Fri: 08:00-11:30, 13:30-16:30
Sat: 08:00-11:30

Person in charge

Ms. Tran Thi At, Ms. Nguyen Thi Yen

Office staff
Tel: +84 4 3823 2313
Email: support@qhkt.gov.vn

Expected results

Receipt of application file (HAUPA1) 01 - Receipt of application file (HAUPA1)

Requirements

Natural persons Corporate investor
A. For all cases:
1. Request for agreement on planning location (Vn)
Request for agreement on planning location (Vn) (original)
2. Written explanation for investment intention
Written explanation for investment intention (original)
location plan, land using scale, content of construction works investment: construction area, floor area, land area, technical infrastructure demand, exclusive demands of the construction works (if any), construction plan, investment capital plan
3. Authenticated copy of document on investor appointment
Authenticated copy of document on investor appointment
4. 01 - Libre deuda de patente
Land map (original)
as recommended by the investors
5. 01 - Libre deuda de patente
Passport or Vietnamese ID card of the person submitting application file (original)
to present at the counter
B. Additional documents:
I. For functional infrastructure work (such as waste water treatment plant, water supplying plant, 110 Kw or higher power transformer station, bus station, urban railway...)
1.
Opinion on location scale of State management competent authorities (an authentic copy)
II. For foreign corporate investors, supplement (for Vietnamese corporate investors, the legalized copy and Vietnamese version of following documents shall be replaced by authenticated copy only)
1. 01 - Libre deuda de patente
Letter of introduction (original)
or Power of attorney (2)
Power of attorney (2) (original)
of the investors for the person submitting the application file
2. 01 - Libre deuda de patente
Consular legalized copy of certificate of incorporation
or certificate of business registration or equivalent documents to define legal status of the investors
3. 01 - Libre deuda de patente
Certified translation of legalized copy of certificate of incorporation
or certificate of business registration or equivalent documents to define legal status of the investors
III. For individual investors,supplement:
1. 01 - Libre deuda de patente
Authenticated copy of passport or Vietnamese ID card of individual investor

Time frame

Waiting time in queue: Max. 10mn
Attention at counter: Min. 5mn - Max. 30mn
Waiting time until next step: Max. 5 days

Legal justification

1. Law No.16/2003/QH11 of the National Assembly on Construction
Law No.16/2003/QH11 of the National Assembly on Construction
2. Law No. 30/2009/QH12  on Urban Planning
Law No. 30/2009/QH12 on Urban Planning
Article 70
3. Decision No. 09/2012/QĐ-UBND of Hanoi People's Committee dated May 21, 2012, on the management of investment and construction of projects of investment in Hanoi
Decision No. 09/2012/QĐ-UBND of Hanoi People's Committee dated May 21, 2012, on the management of investment and construction of projects of investment in Hanoi
Article 4.2.b
4. Decision No. 1858/QD-UBND of Hanoi People's Committee dated April 22, 2011 on administrative procedures of Hanoi Authority For Planning and Architecture
Decision No. 1858/QD-UBND of Hanoi People's Committee dated April 22, 2011 on administrative procedures of Hanoi Authority For Planning and Architecture
Section II.I

Additional information

Number of application file: 1 set and drawings enclosed with CD recorded all document and drawing contents (in format of AutoCAD, Acrobat for drawings and Word, Excel, Acrobat for documents).

Recourse: Hanoi Authority for Urban Planning & Architecture

Entity in charge

Hanoi Authority for Urban Planning & Architecture

31b Trang Thi Street, Hoan Kiem District , Hanoi
Tel: +84 4 3823 2313/+84 4 3823 2312
Fax: +84 4 3823 0074
Email: support@qhkt.gov.vn
Website: http://qhkthn.gov.vn/

Unit in charge

Administration Office

Mon: 08:00-12:00, 13:00-17:00
Tue: 08:00-12:00, 13:00-17:00
Wed: 08:00-12:00, 13:00-17:00
Thu: 08:00-12:00, 13:00-17:00
Fri: 08:00-12:00, 13:00-17:00

Person in charge

Mr. Bui Van Bac - Deputy office manager

Tel: + 84 4 3823 2313