List of steps
(Total number of steps: 80)
Meet HAPI
Define location  (1)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Propose to take project into the list of projects for investor selection  (1)
Obtain document on investor appointment  (2)
Obtain authenticated copies of document on investor appointment  (2)
Obtain agreement on location plan  (2)
Obtain current condition land map  (1)
Define red line boundaries and technical indications  (3)
Obtain construction planning certificate (or planning information)  (2)
Obtain planning license  (2)
Obtain master plan and and preliminary architectural plan approval  (2)
Obtain 1/500-scale detailed construction-planning tasks appraisal and approval  (2)
Obtain 1/500-scale detailed construction-planning blueprints approval  (2)
Obtain information on land use plan  (2)
Obtain Investment Certificate  (3)
Receive evaluation document on land use demand, conditions for land lease, land assignement  (1)
Obtain authenticated copies of Investment Certificate  (2)
Make seal and notify seal specimen  (3)
40
Make seal
Obtain certificate of tax registration  (2)
Open bank account  (1)
Publish in newspaper  (1)
Prepare construction investment project  (1)
Obtain approval on environmental impact assessment  (3)
Prepare construction dossier (including: fire fighting design dossier)  (1)
Obtain fire prevention and fighting appraisal and approval (for conceptual design dossier)  (2)
Obtain opinions on conceptual design  (2)
Obtain land lease decision  (2)
Receive notification on land rental amount (for land plot value of less than 30 billion Dongs)  (1)
Sign land lease contract  (3)
Pay land rental  (1)
Make landmarks definition plan for extracted map of land plot  (3)
Receive land plot on site and obtain extracted map of land plot  (4)
Obtain land use rightcertificate  (5)
Obtain fire prevention and fighting approval  (2)
Request for construction design evaluation (for a number of construction work as provided by law)  (2)
Obtain construction permit  (2)

Preview & Print

Properties
 
Meet HAPI
(last modified: 6/28/2015)
This step is optional

Contact details

Entity in charge

Hanoi Authority for Planning & Investment (HAPI)

16 Cat Linh Street, Dong Da District , Hanoi
Tel: +84 43 825 6637
Email: sokhdthanoi@hapi.gov.vn
Website: http://www.hapi.gov.vn

Unit in charge

Foreign Investment Division

Mon: 08:00-12:00, 13:00-17:00
Tue: 08:00-12:00, 13:00-17:00
Wed: 08:00-12:00, 13:00-17:00
Thu: 08:00-12:00, 13:00-17:00
Fri: 08:00-12:00, 13:00-17:00

Person in charge

Mr. Nguyen Anh Dzung, Head of Division

Tel: +84 43 826 0257

Expected results

Request for issuance of investment certificate Request for issuance of investment certificate
Guidelines on filling in forms for investors 01 - Guidelines on filling in forms for investors

Time frame

Waiting time in queue: Max. 5mn
Attention at counter: Min. 20mn - Max. 1h

Additional information

It is recommended to come with clear information on the investment project (scope, field, duration, etc.)

Who certified this information ?

Huu Luong  NGUYEN (MR.), 21/11/2014

Recourse: Hanoi Authority for Planning & Investment (HAPI)

Entity in charge

Hanoi Authority for Planning & Investment (HAPI)

16 Cat Linh Street, Dong Da District , Hanoi
Tel: +84 43 825 6637
Email: sokhdthanoi@hapi.gov.vn
Website: http://www.hapi.gov.vn

Unit in charge

Administration Office

Mon: 08:00-12:00, 13:00-17:00
Tue: 08:00-12:00, 13:00-17:00
Wed: 08:00-12:00, 13:00-17:00
Thu: 08:00-12:00, 13:00-17:00
Fri: 08:00-12:00, 13:00-17:00

Person in charge

Mr. Nguyen Huu Luong

Deputy Office Manager
Tel: + 84 43 825 6637
Email: luongnh@hapi.gov.vn
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License