List of steps
(Total number of steps: 80)
Meet HAPI
Define location  (1)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Propose to take project into the list of projects for investor selection  (1)
Obtain document on investor appointment  (2)
Obtain authenticated copies of document on investor appointment  (2)
Obtain agreement on location plan  (2)
Obtain current condition land map  (1)
Define red line boundaries and technical indications  (3)
Obtain construction planning certificate (or planning information)  (2)
Obtain planning license  (2)
Obtain master plan and and preliminary architectural plan approval  (2)
Obtain 1/500-scale detailed construction-planning tasks appraisal and approval  (2)
Obtain 1/500-scale detailed construction-planning blueprints approval  (2)
Obtain information on land use plan  (2)
Obtain Investment Certificate  (3)
Receive evaluation document on land use demand, conditions for land lease, land assignement  (1)
Obtain authenticated copies of Investment Certificate  (2)
Make seal and notify seal specimen  (3)
40
Make seal
Obtain certificate of tax registration  (2)
Open bank account  (1)
Publish in newspaper  (1)
Prepare construction investment project  (1)
Obtain approval on environmental impact assessment  (3)
Prepare construction dossier (including: fire fighting design dossier)  (1)
Obtain fire prevention and fighting appraisal and approval (for conceptual design dossier)  (2)
Obtain opinions on conceptual design  (2)
Obtain land lease decision  (2)
Receive notification on land rental amount (for land plot value of less than 30 billion Dongs)  (1)
Sign land lease contract  (3)
Pay land rental  (1)
Make landmarks definition plan for extracted map of land plot  (3)
Receive land plot on site and obtain extracted map of land plot  (4)
Obtain land use rightcertificate  (5)
Obtain fire prevention and fighting approval  (2)
Request for construction design evaluation (for a number of construction work as provided by law)  (2)
Obtain construction permit  (2)

Preview & Print

Properties
 
59
Receive land lease contract draft
(last modified: 6/28/2015)

Expected results

Draft of land lease contract draft Draft of land lease contract draft

Legal justification

1. Law No. 45/2013/QH13 dated November 29, 2013 of the National Assembly on Land
Law No. 45/2013/QH13 dated November 29, 2013 of the National Assembly on Land
Article 56
2. Decree No. 43/2014/NĐ-CP dated May 5, 2014 detailing the implementation of a number of articles of the Land on Land
Decree No. 43/2014/ND-CP of the Government dated May 5, 2014 detailing the implementation of a number of articles of the Land on Land
articles 14, 68.3
3. Decision 21/2014/QD-UBND of Hanoi People's Committee dated June 20, 2014 on land recovery, land assignment, land lease... for implementation of investment project in Hanoi
Decision No. 21/2014/QD-UBND of Hanoi People's Committee dated June 20, 2014 on land recovery, land assignment, land lease... for implementation of investment project in Hanoi
Article 16
4. Decision No. 74/2014/QD-UBND of Hanoi People's Committee dated October 02, 2014 on determining specific land price
Decision No. 74/2014/QD-UBND of Hanoi People's Committee dated October 02, 2014 on determining specific land price
Article 4

Additional information

Hanoi Natural Resources & Environment Department will prepare and send the draft of land lease contract by post to the company for their signature within 05 working days from the date of receiving notification on land rental from Tax Department.

Who certified this information ?

Trong Dong NGUYEN (MR), 27/03/2015

Recourse: Hanoi Natural Resources & Environment Department

Entity in charge

Hanoi Natural Resources & Environment Department

18 Huynh Thuc Khang Street - Dong Da District , Hanoi
Tel: + 84 4 3773 1566
Fax: +84 4 3773 1566
Website: http://tnmtnd.hanoi.gov.vn/

Unit in charge

Reception Unit

Mon: 08:00-12:00, 13:00-17:00
Tue: 08:00-12:00, 13:00-17:00
Wed: 08:00-12:00, 13:00-17:00
Thu: 08:00-12:00, 13:00-17:00
Fri: 08:00-12:00, 13:00-17:00

Person in charge

Mr. Trinh Que Lam

Executive
Tel: +84 4 3773 5113