Obtain certified copies of foreign documents
(2)
Obtain consular legalized copies of foreign documents
(3)
Obtain certified translation of documents
(2)
Obtain authenticated copies of passports or Vietnamese ID cards
(2)
Propose to take project into the list of projects for investor selection
(1)
Obtain document on investor appointment
(2)
Obtain authenticated copies of document on investor appointment
(2)
Obtain agreement on location plan
(2)
Obtain current condition land map
(1)
Define red line boundaries and technical indications
(3)
Obtain construction planning certificate (or planning information)
(2)
Obtain planning license
(2)
Obtain master plan and and preliminary architectural plan approval
(2)
Obtain 1/500-scale detailed construction-planning tasks appraisal and approval
(2)
Obtain 1/500-scale detailed construction-planning blueprints approval
(2)
Obtain information on land use plan
(2)
Obtain Investment Certificate
(3)
Receive evaluation document on land use demand, conditions for land lease, land assignement
(1)
Obtain authenticated copies of Investment Certificate
(2)
Make seal and notify seal specimen
(3)
Obtain certificate of tax registration
(2)
Prepare construction investment project
(1)
Obtain approval on environmental impact assessment
(3)
Prepare construction dossier (including: fire fighting design dossier)
(1)
Obtain fire prevention and fighting appraisal and approval (for conceptual design dossier)
(2)
Obtain opinions on conceptual design
(2)
Obtain land lease decision
(2)
Receive notification on land rental amount (for land plot value of less than 30 billion Dongs)
(1)
Sign land lease contract
(3)
Make landmarks definition plan for extracted map of land plot
(3)
Receive land plot on site and obtain extracted map of land plot
(4)
Obtain land use rightcertificate
(5)
Obtain fire prevention and fighting approval
(2)
Request for construction design evaluation (for a number of construction work as provided by law)
(2)
Obtain construction permit
(2)