Requirements
Natural persons
Corporate investor
1.
Application for master plan and preliminary architectural plan approval (original)
2.
Document on investor appointment (an authentic copy)
3.
Current condition land map (an authentic copy)
4.
Red line boundaries drawing (original)
scale 1/500-1/200 made by authorized organization within the most 3 recent years
5.
Technical indications of land (original)
6.
Master plan drawings (2 original )
scale 1/500-1/200 made on current condition land map and red line boundaries drawing certified by consulting company and investor. Master plan content defines legal base, technical specifications...
7.
Written explanation (original)
8.
Preliminary architectural plan (2 original )
9.
Practicing certificate (an authentic copy)
of designing institution or individual
10.
Passport or Vietnamese ID card of the person submitting application file (original)
(to present at the counter)
I. For foreign corporate investors, supplement (for Vietnamese corporate investors, the legalized copy and Vietnamese version of following documents shall be replaced by authenticated copy only)
1.
Letter of introduction (original)
or
Power of attorney (2) (original)
of the investors for the person submitting the application file
2.
Consular legalized copy of certificate of incorporation
or certificate of business registration or equivalent documents to define legal status of the investors
3.
Certified translation of legalized copy of certificate of incorporation
or certificate of business registration or equivalent documents to define legal status of the investors
II. For individual investors, supplement:
1.
Authenticated copy of passport or Vietnamese ID card of individual investor
III. For functional infrastructure work (such as waste water treatment plant, water supplying plant, 110 Kw or higher power transformer station, bus station, urban railway...) supplement
1.
Technology chain drawings approved by functional State management competent authorities (an authentic copy)
IV. For master plan on land plot that investor does not have document proving land use rights, supplement:
1.
Agreement on location plan (an authentic copy)
2.
Construction planning certificate (Simple copy)
V. For master plan on land plot that investor has document proving land use rights, supplement:
1.
Construction planning certificate (Simple copy)
2.
Document on land use rights (an authentic copy)
VI. For master plan or detailed plan already approved by competent authority, supplement
1.
Master plan drawings (an authentic copy)
or detailed plan drawings approved by competent authority
Time frame
Waiting time in queue:
Max. 10mn
Attention at counter:
Min. 5mn - Max. 30mn
Waiting time until next step:
Max. 5 days
Legal justification
1.
Law No.16/2003/QH11 of the National Assembly on Construction
articles 35, 36, 37
2.
Law No. 30/2009/QH12 on Urban Planning
3.
Decree No. 37/2010/ND-CP of the Government dated April 07, 2010 on the formulation, appraisal, approval, and management of urban planning
Article 14
4.
Decree No. 38/2010/ND-CP of the Government dated Apirl 07, 2010, on management of urban space, architecture and landscapes
Article 6-21
5.
Decision No. 21/2005/QD-BXD of the Ministry of Construction on symbols system of drawings used in planning dossier
Article Apdx.
6.
Decision No. 09/2012/QĐ-UBND of Hanoi People's Committee dated May 21, 2012, on the management of investment and construction of projects of investment in Hanoi
Article 4.2.b
7.
Decision No. 1858/QD-UBND of Hanoi People's Committee dated April 22, 2011 on administrative procedures of Hanoi Authority For Planning and Architecture
Section II.III
8.
Decision No. 72/2014/QD-UBND of Hanoi People's Committee dated September 17, 2014 promulgating regulations on making, appraising, approving plan in Hanoi
articles 3.3, 7
Additional information
Number of application file: 1 set and drawings enclosed with CD recorded all document and drawing contents (in format of AutoCAD, Acrobat for drawings and Word, Excel, Acrobat for documents).
For an investment project having area of 5 ha or more (area of 2 ha or more for housing construction investment project), it is required to make and obtain approval on detailed construction-planning blueprint instead of obtaining master plan approval. Hanoi Authority for Urban Planning & Architecture will appraise the detailed construction-planning blueprint and submit to Hanoi People’s Committee for approval.