Invalid column name 'oldid'.
List of steps
(Total number of steps: 80)
Meet HAPI
Define location  (1)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Propose to take project into the list of projects for investor selection  (1)
Obtain document on investor appointment  (2)
Obtain authenticated copies of document on investor appointment  (2)
Obtain agreement on location plan  (2)
Obtain current condition land map  (1)
Define red line boundaries and technical indications  (3)
Obtain construction planning certificate (or planning information)  (2)
Obtain planning license  (2)
Obtain master plan and and preliminary architectural plan approval  (2)
Obtain 1/500-scale detailed construction-planning tasks appraisal and approval  (2)
Obtain 1/500-scale detailed construction-planning blueprints approval  (2)
Obtain information on land use plan  (2)
Obtain Investment Certificate  (3)
Receive evaluation document on land use demand, conditions for land lease, land assignement  (1)
Obtain authenticated copies of Investment Certificate  (2)
Make seal and notify seal specimen  (3)
40
Make seal
Obtain certificate of tax registration  (2)
Open bank account  (1)
Publish in newspaper  (1)
Prepare construction investment project  (1)
Obtain approval on environmental impact assessment  (3)
Prepare construction dossier (including: fire fighting design dossier)  (1)
Obtain fire prevention and fighting appraisal and approval (for conceptual design dossier)  (2)
Obtain opinions on conceptual design  (2)
Obtain land lease decision  (2)
Receive notification on land rental amount (for land plot value of less than 30 billion Dongs)  (1)
Sign land lease contract  (3)
Pay land rental  (1)
Make landmarks definition plan for extracted map of land plot  (3)
Receive land plot on site and obtain extracted map of land plot  (4)
Obtain land use rightcertificate  (5)
Obtain fire prevention and fighting approval  (2)
Request for construction design evaluation (for a number of construction work as provided by law)  (2)
Obtain construction permit  (2)

Preview & Print

Properties
 
32
Submit application for land use plan
(last modified: 6/28/2015)

Timeframe ( ver detalles )

Espera hasta paso siguiente

10 mn  -  1h 30 mn
0 days  -  7 days

Contact details

Entity in charge

Hanoi Natural Resources & Environment Department

18 Huynh Thuc Khang Street - Dong Da District , Hanoi
Tel: + 84 4 3773 1566
Fax: +84 4 3773 1566
Website: http://tnmtnd.hanoi.gov.vn/

Unit in charge

Reception & Release Desk (DONRE)

Mon: 08:00-12:00, 13:00-17:00
Tue: 08:00-12:00, 13:00-17:00
Wed: 08:00-12:00, 13:00-17:00
Thu: 08:00-12:00, 13:00-17:00
Fri: 08:00-12:00, 13:00-17:00
Sat: 08:00-12:00

Person in charge

Ms. Pham Thi Hai Yen

Executive
Tel: + 84 4 3773 1563

Expected results

Receipt of application file (N3) 01 - Receipt of application file (N3)

Requirements

Natural persons Corporate investor
1.
Application for information on land use plan (original)
2.
Legal document on land use (if any) (Simple copy)
or
Document showing land use demand (Simple copy)
3. 01 - Libre deuda de patente
Passport or Vietnamese ID card of the person submitting application file (original)
(to present at the counter)
4. Power of attorney (2)
Power of attorney (2) (original)
of the investor to the person submitting the application file
For individual investors,supplement:
1. 01 - Libre deuda de patente
Authenticated copy of passport or Vietnamese ID card of individual investor
For foreign corporate investors, supplement (for Vietnamese corporate investors, the legalized copy and Vietnamese version of following documents shall be replaced by authenticated copy only)
1. 01 - Libre deuda de patente
Consular legalized copy of certificate of incorporation
or certificate of business registration or equivalent documents
2. 01 - Libre deuda de patente
Certified translation of legalized copy of certificate of incorporation
or certificate of business registration or equivalent documents

Time frame

Waiting time in queue: Min. 5mn - Max. 1h
Attention at counter: Min. 5mn - Max. 30mn
Waiting time until next step: Max. 7 days

Legal justification

1. Decision 21/2014/QD-UBND of Hanoi People's Committee dated June 20, 2014 on land recovery, land assignment, land lease... for implementation of investment project in Hanoi
Decision No. 21/2014/QD-UBND of Hanoi People's Committee dated June 20, 2014 on land recovery, land assignment, land lease... for implementation of investment project in Hanoi
Article 6
2. Decision No. 7122/QD-UBND of Hanoi People's Committee dated 22/11/2013 on approving the project of providing information on land use plan
Decision No. 7122/QD-UBND of Hanoi People's Committee dated 22/11/2013 on approving the project of providing information on land use plan
Article II.4

Who certified this information ?

Trong Dong NGUYEN (MR), 27/03/2015

Recourse: Hanoi Natural Resources & Environment Department

Entity in charge

Hanoi Natural Resources & Environment Department

18 Huynh Thuc Khang Street - Dong Da District , Hanoi
Tel: + 84 4 3773 1566
Fax: +84 4 3773 1566
Website: http://tnmtnd.hanoi.gov.vn/

Unit in charge

Reception Unit

Mon: 08:00-12:00, 13:00-17:00
Tue: 08:00-12:00, 13:00-17:00
Wed: 08:00-12:00, 13:00-17:00
Thu: 08:00-12:00, 13:00-17:00
Fri: 08:00-12:00, 13:00-17:00

Person in charge

Mr. Trinh Que Lam

Executive
Tel: +84 4 3773 5113
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License