Requirements
Representatives
1.
Official letter for entering into consulting contract with HUPI (original)
2.
Relief map (original)
or
Cadastral map presenting relief elements (original)
or
Current condition land map (original)
3.
Passport or Vietnamese ID card of the person submitting application file (original)
(to present at the counter)
1.
Authenticated copy of document on investor appointment
For land plot currently using
1.
Document on land use rights (an authentic copy)
For case of authorization to other person submitting application file
1.
Authorization document
given by investor to person or organization submitting application file
2.
Letter of introduction (original)
of the authorized organization to the person directly submitting application file
Time frame
Waiting time in queue:
Min. 10mn
Attention at counter:
Min. 5mn - Max. 30mn
Waiting time until next step:
Min. 1 day - Max. 3 days
Legal justification
1.
Law No.16/2003/QH11 of the National Assembly on Construction
Article 33
2.
Law No. 30/2009/QH12 on Urban Planning
Article 56
3.
Decree No. 37/2010/ND-CP of the Government dated April 07, 2010 on the formulation, appraisal, approval, and management of urban planning
Article 20
4.
Decree No. 08/2005/ND-CP of the Government dated January 24, 2005 on construction planning
Article 56
5.
Circular No. 07/2008/TT-BXD dated April 07, 2008 of the Ministry of Construction guiding the elaboration, evaluation, approval and management of construction planning
Article 41
6.
Decision 23/2008/QD-UBND
Article 2.2.d
7.
Decision 2832/QD-UBND
Article 1
8.
Decision No. 09/2012/QĐ-UBND of Hanoi People's Committee dated May 21, 2012, on the management of investment and construction of projects of investment in Hanoi
Article Appendixes
9.
Official Letter 7393
Article 1
10.
Decision No. 72/2014/QD-UBND of Hanoi People's Committee dated September 17, 2014 promulgating regulations on making, appraising, approving plan in Hanoi
Article 17.6