List of steps
(Total number of steps: 69)
Meet HAPI
Legalize foreign documents  (3)
Translate foreign documents  (2)
Define location  (1)
Propose to supplement investment project to the list of investment projects  (1)
Request to be appointed as investor of investment project  (2)
Obtain current condition land map  (1)
Prepare construction dossier (including: fire fighting design dossier)  (1)
Obtain agreement on location plan  (2)
Define red line boundaries and technical infrastructure indications  (3)
Obtain construction planning certificate (or planning information)  (2)
Obtain planning license  (2)
Obtain master plan and and preliminary architectural plan approval  (2)
Obtain 1/500-scale detailed construction-planning tasks appraisal and approval  (2)
Obtain 1/500-scale detailed construction-planning blueprints appraisal and approval  (2)
Obtain Investment Certificate  (3)
Obtain seal and seal registration Certification  (2)
Obtain certificate of tax registration  (2)
Publish in newspaper  (1)
Open bank account  (1)
Obtain approval on environmental impact assessment  (3)
Obtain fire prevention and fighting appraisal and approval (for conceptual design dossier)  (2)
Obtain opinions on conceptual design  (2)
Obtain fire prevention and fighting approval (for construction drawings dossiers)  (2)
Obtain land recovery notice; Request to set up compensation, support and resettlement council  (1)
Obtain approval on instruction for landmarks definition for compensation, support and resettlement  (2)
Make landmarks definition plan  (1)
Receive landmarks on site  (2)
Make detailed plan for compensation, support and resettlement  (1)
Request for land lease  (2)
Making payment upon approved detailed plan for compensation, support and resettlement  (1)
Obtain approval on instruction for landmarks definition for calculating land rental  (2)
Receive the land plot on site  (1)
Determine land rental, land rental rate  (4)
Sign land lease contract  (2)
Declare and pay land rental  (1)
Obtain extract of land plot location  (2)
Obtain land use right, house and land-attached asset ownership certificate  (3)

Preview & Print

Properties
 
43
Submit application for fire prevention and fighting approval (for technical design or design drawings for execution dossiers)
(last modified: 10/12/2014)

Timeframe ( ver detalles )

Espera hasta paso siguiente

5 mn  -  30 mn
0 days  -  3 days

Contact details

Entity in charge

Hanoi Fire Fighting and Prevention Police

1, 2 Fl. CT14A2 Building, Nam Thang Long New Town, Lac Long Quan Road, Tay Ho District , Hanoi
Tel: +84 4 3939 7981

Unit in charge

Reception & Release Desk (Fire Prevention Police)

Mon: 08:00-12:00, 13:00-17:00
Tue: 08:00-12:00, 13:00-17:00
Wed: 08:00-12:00, 13:00-17:00
Thu: 08:00-12:00, 13:00-17:00
Fri: 08:00-12:00, 13:00-17:00
Sat: 08:00-12:00

Person in charge

Mr. Tran Tuan Dung

Officer
Tel: +84 936 468 789

Expected results

Receipt of application file for fire prevention 01 - Receipt of application file for fire prevention

Requirements

1. Request for fire prevention and fighting appraisal and approval
Request for fire prevention and fighting appraisal and approval (original)
2. 01 - Libre deuda de patente
Drawings and explanations of technical design or design drawings for execution (an authentic copy)
or certified by company (investor) demonstrating the requirements for fire prevention and fighting solutions prescribed in Clause 1, 2, 3, 4, 5 and 6 Article 13 of Decree No. 79/2014/ND-CP
3. 01 - Libre deuda de patente
Cost estimation of total investment capital of project, building works (an authentic copy)
or certified by company (investor)
Written approval on planning of competent authority:
For case of authorization
1. Power of attorney (2)
Power of attorney (2) (original)

Time frame

For technical design and construction drawings for execution, the time limits for fire prevention and fighting design appraisal and approval calculated from fully submitting the valid dossier are as follows:
- Within 15 working days for projects and constructions of Group A;
- Within 10 working days for projects and constructions of Group B and Group C.
The classification of projects and constructions to Group A, B, C shall be carried out under the Government’s provisions on construction investment project management.
Waiting time in queue: Max. 15mn
Attention at counter: Min.  5mn - Max.  15mn
Waiting time until next step: Max.  3 days

Legal justification

1. Law No. 27/2001/QH10 on Fire prevention and Fighting of National Assembly (as amended by Law No. 40/2013/QH13)
Law No. 27/2001/QH10 on Fire prevention and Fighting of National Assembly (as amended by Law No. 40/2013/QH13)
Article 15
2. Decree No. 79/2014/ND-CP of the Government dated Jul 31, 2014 detailing the implementation of a number of articles of the Law on fire prevention and fighting and Law on amendment of a number of articles of the Law on fire prevention and fighting
Decree No. 79/2014/ND-CP of the Government dated Jul 31, 2014 detailing the implementation of a number of articles of the Law on fire prevention and fighting and Law on amendment of a number of articles of the Law on fire prevention and fighting
articles 13, 15

Additional information

Number of application file: 2 sets. The application file must be certified by investors and translated the explanations into Vietnamese if they are in foreign language.
Project and works prescribed in Appendix IV to Decree No. 79/2014/ND-CP, when being newly constructed, renovated or utility-related changed, must be appraised and approved in term of fire prevention and fighting design by fire prevention and fighting police agencies.
Based on the nature and scale of project or construction works, fire prevention and fighting police agencies may either fire prevention and fighting police department of Ministry of Public Security or fire prevention and fighting police department of Hanoi People's Committee. We only describe here case that the appraisal and approval of fire prevention and fighting design is made by fighting police department of Hanoi People's Committee.
Fire prevention and fighting police department shall issue certificate of fire prevention and fighting for technical design or design drawings for execution dossiers.

Recourse: Hanoi Fire Fighting and Prevention Police

Entity in charge

Hanoi Fire Fighting and Prevention Police

1, 2 Fl. CT14A2 Building, Nam Thang Long New Town, Lac Long Quan Road, Tay Ho District , Hanoi
Tel: +84 4 3939 7981

Unit in charge

Fire Prevention Guide Division

Mon: 08:00-12:00, 13:00-17:00
Tue: 08:00-12:00, 13:00-17:00
Wed: 08:00-12:00, 13:00-17:00
Thu: 08:00-12:00, 13:00-17:00
Fri: 08:00-12:00, 13:00-17:00
Sat: 08:00-12:00

Person in charge

Mr. Vu Duc Hung

Head of fire prevention appraisal guide and checking team
Tel: + 84 912 591 916
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License