List of steps
(Total number of steps: 69)
Meet HAPI
Legalize foreign documents  (3)
Translate foreign documents  (2)
Define location  (1)
Propose to supplement investment project to the list of investment projects  (1)
Request to be appointed as investor of investment project  (2)
Obtain current condition land map  (1)
Prepare construction dossier (including: fire fighting design dossier)  (1)
Obtain agreement on location plan  (2)
Define red line boundaries and technical infrastructure indications  (3)
Obtain construction planning certificate (or planning information)  (2)
Obtain planning license  (2)
Obtain master plan and and preliminary architectural plan approval  (2)
Obtain 1/500-scale detailed construction-planning tasks appraisal and approval  (2)
Obtain 1/500-scale detailed construction-planning blueprints appraisal and approval  (2)
Obtain Investment Certificate  (3)
Obtain seal and seal registration Certification  (2)
Obtain certificate of tax registration  (2)
Publish in newspaper  (1)
Open bank account  (1)
Obtain approval on environmental impact assessment  (3)
Obtain fire prevention and fighting appraisal and approval (for conceptual design dossier)  (2)
Obtain opinions on conceptual design  (2)
Obtain fire prevention and fighting approval (for construction drawings dossiers)  (2)
Obtain land recovery notice; Request to set up compensation, support and resettlement council  (1)
Obtain approval on instruction for landmarks definition for compensation, support and resettlement  (2)
Make landmarks definition plan  (1)
Receive landmarks on site  (2)
Make detailed plan for compensation, support and resettlement  (1)
Request for land lease  (2)
Making payment upon approved detailed plan for compensation, support and resettlement  (1)
Obtain approval on instruction for landmarks definition for calculating land rental  (2)
Receive the land plot on site  (1)
Determine land rental, land rental rate  (4)
Sign land lease contract  (2)
Declare and pay land rental  (1)
Obtain extract of land plot location  (2)
Obtain land use right, house and land-attached asset ownership certificate  (3)

Preview & Print

Properties
 
36
Prepare EIA report
(last modified: 29/05/2015)

Costs

( ver detalles )

Espera hasta paso siguiente

VND 20000000
30 days  -  45 days

Contact details

Entity in charge

Any authorized EIA report consulting companies


List of some environment consulting companies (not exhaustive) List of some environment consulting companies (not exhaustive)

Expected results

EIA report EIA report

Costs

Cost detail

Hypothesis

VND 20,000,000
Fee for making EIA report for reference only
This cost is depended on size and nature of the project. The cost given here is for reference only.

Time frame

Waiting time until next step: Min.  30 days - Max.  45 days

Legal justification

1. Law No. 52/2005/QH11 of the National Assembly on Environmental Protection
Law No. 52/2005/QH11 of the National Assembly on Environmental Protection
articles 18, 19, 20
2. Decree No. 29/2011/ND-CP of the Government dated April 8, 2011 on strategic environmental assessment, environmental impact assessment and environmental protection commitment
Decree No. 29/2011/ND-CP of the Government dated April 8, 2011 on strategic environmental assessment, environmental impact assessment and environmental protection commitment
articles 12, 13, 14, 15, 16, 17
3. Circular No. 26/2011/TT-BTNMT of the Ministry of Natural Resources and Environment detailing a number of articles of the Government’s Decree No. 29/2011/ND-CP dated April 8, 2011 on strategic environmental assessment, environmental impact assessment and environmental protection commitment
Circular No. 26/2011/TT-BTNMT of the Ministry of Natural Resources and Environment detailing a number of articles of the Government’s Decree No. 29/2011/ND-CP dated April 8, 2011 on strategic environmental assessment, environmental impact assessment and environmental protection commitment
articles 10, 12

Additional information

Projects subject to making of EIA report are listed in Appendix II to Decree 29/2011/ND-CP. EIA report must be appraised and approved by provincial people’s committee, except projects that are appraised and approved by the Ministry of Natural Resources and Environment as listed in Appendix III to Decree 29/2011/ND-CP. For other projects, the company shall have to make and register the written environment protection commitment to the district-level people’s Committee where the project is located.
A company being the owner of an investment project for which an environmental impact assessment (EIA) report must be formulated shall carry out itself, or hire a consultancy organization which satisfies all conditions stipulated in Article 8 of Decree 29/2011/ND-CP to carry out EIA and formulate an EIA report for the project.
We only describe here procedures related to making and requesting for EIA report approval at Hanoi People’s Committee.