List of steps
(Total number of steps: 69)
Meet HAPI
Legalize foreign documents  (3)
Translate foreign documents  (2)
Define location  (1)
Propose to supplement investment project to the list of investment projects  (1)
Request to be appointed as investor of investment project  (2)
Obtain current condition land map  (1)
Prepare construction dossier (including: fire fighting design dossier)  (1)
Obtain agreement on location plan  (2)
Define red line boundaries and technical infrastructure indications  (3)
Obtain construction planning certificate (or planning information)  (2)
Obtain planning license  (2)
Obtain master plan and and preliminary architectural plan approval  (2)
Obtain 1/500-scale detailed construction-planning tasks appraisal and approval  (2)
Obtain 1/500-scale detailed construction-planning blueprints appraisal and approval  (2)
Obtain Investment Certificate  (3)
Obtain seal and seal registration Certification  (2)
Obtain certificate of tax registration  (2)
Publish in newspaper  (1)
Open bank account  (1)
Obtain approval on environmental impact assessment  (3)
Obtain fire prevention and fighting appraisal and approval (for conceptual design dossier)  (2)
Obtain opinions on conceptual design  (2)
Obtain fire prevention and fighting approval (for construction drawings dossiers)  (2)
Obtain land recovery notice; Request to set up compensation, support and resettlement council  (1)
Obtain approval on instruction for landmarks definition for compensation, support and resettlement  (2)
Make landmarks definition plan  (1)
Receive landmarks on site  (2)
Make detailed plan for compensation, support and resettlement  (1)
Request for land lease  (2)
Making payment upon approved detailed plan for compensation, support and resettlement  (1)
Obtain approval on instruction for landmarks definition for calculating land rental  (2)
Receive the land plot on site  (1)
Determine land rental, land rental rate  (4)
Sign land lease contract  (2)
Declare and pay land rental  (1)
Obtain extract of land plot location  (2)
Obtain land use right, house and land-attached asset ownership certificate  (3)

Preview & Print

Properties
 
3
Collect legalized documents

Contact details

Entity in charge

Consular Department - Ministry of Foreign Affairs

40 Tran Phu street, Ba Dinh district , Hanoi
Tel: +84 43 799 3416/+84 43 799 3340
Email: [email protected]
Website: http://lanhsuvietnam.gov.vn/default.aspx

Unit in charge

Division of Consular Legalization and Certification

Mon: 08:30-11:30, 14:00-16:30
Tue: 08:30-11:30, 14:00-15:30
Wed: 08:30-11:30, 14:00-16:30
Thu: 08:30-11:30, 14:00-16:30
Fri: 08:30-11:30, 14:00-16:30
Sat: 08:30-11:30

Person in charge

Ms. Pham Thi Bich Ngoc

Executive
Tel: +84 43 799 3416

Expected results

Legalized document 01 - Legalized document

Requirements

1. 01 - Libre deuda de patente
Consular legalization receipt (paid)
2. 01 - Libre deuda de patente
Payment receipt (consular legalization) (original)
3. 01 - Libre deuda de patente
Passport or ID card (original)
of the person named in the receipt of application for consular ligalization

Time frame

Waiting time in queue: Min.  10mn - Max. 30mn
Attention at counter: Min.  10mn - Max.  15mn

Recourse: Consular Department - Ministry of Foreign Affairs

Entity in charge

Consular Department - Ministry of Foreign Affairs

40 Tran Phu street, Ba Dinh district , Hanoi
Tel: +84 43 799 3416/+84 43 799 3340
Email: [email protected]
Website: http://lanhsuvietnam.gov.vn/default.aspx

Unit in charge

Division of Consular Legalization and Certification

Mon: 08:30-11:30, 14:00-16:30
Tue: 08:30-11:30, 14:00-15:30
Wed: 08:30-11:30, 14:00-16:30
Thu: 08:30-11:30, 14:00-16:30
Fri: 08:30-11:30, 14:00-16:30
Sat: 08:30-11:30

Person in charge

Mr. Le Trung Hoa

Head of Division
Tel: +84 43 799 3416