Requirements
Natural persons
Corporate investor
1.
Request for agreement on planning location (Vn) (original)
2.
Written explanation for investment intention (original)
location plan, land using scale, content of construction works investment: construction area, floor area, land area, technical infrastructure demand, exclusive demands of the construction works (if any), construction plan, investment capital plan
3.
Authenticated copy of document on investor appointment
4.
Land map (original)
as recommended by the investors
5.
Passport or Vietnamese ID card of the person submitting application file (original)
to present at the counter
I. For functional infrastructure work (such as waste water treatment plant, water supplying plant, 110 Kw or higher power transformer station, bus station, urban railway...)
1.
Opinion on location scale of State management competent authorities (an authentic copy)
II. For foreign corporate investors, supplement (for Vietnamese corporate investors, the legalized copy and Vietnamese version of following documents shall be replaced by authenticated copy only)
1.
Letter of introduction (original)
or
Power of attorney (2) (original)
of the investors for the person submitting the application file
2.
Consular legalized copy of certificate of incorporation
or certificate of business registration or equivalent documents to define legal status of the investors
3.
Certified translation of legalized copy of certificate of incorporation
or certificate of business registration or equivalent documents to define legal status of the investors
III. For individual investors,supplement:
1.
Authenticated copy of passport or Vietnamese ID card of individual investor
Time frame
Waiting time in queue:
Max. 10mn
Attention at counter:
Min. 5mn - Max. 30mn
Waiting time until next step:
Max. 5 days
Legal justification
1.
Law No.16/2003/QH11 of the National Assembly on Construction
2.
Law No. 30/2009/QH12 on Urban Planning
Article 70
3.
Decision No. 09/2012/QĐ-UBND of Hanoi People's Committee dated May 21, 2012, on the management of investment and construction of projects of investment in Hanoi
Article 4.2.b
4.
Decision No. 1858/QD-UBND of Hanoi People's Committee dated April 22, 2011 on administrative procedures of Hanoi Authority For Planning and Architecture
Section II.I
Additional information
Number of application file: 1 set and drawings enclosed with CD recorded all document and drawing contents (in format of AutoCAD, Acrobat for drawings and Word, Excel, Acrobat for documents).