List of steps
(Total number of steps: 69)
Meet HAPI
Legalize foreign documents  (3)
Translate foreign documents  (2)
Define location  (1)
Propose to supplement investment project to the list of investment projects  (1)
Request to be appointed as investor of investment project  (2)
Obtain current condition land map  (1)
Prepare construction dossier (including: fire fighting design dossier)  (1)
Obtain agreement on location plan  (2)
Define red line boundaries and technical infrastructure indications  (3)
Obtain construction planning certificate (or planning information)  (2)
Obtain planning license  (2)
Obtain master plan and and preliminary architectural plan approval  (2)
Obtain 1/500-scale detailed construction-planning tasks appraisal and approval  (2)
Obtain 1/500-scale detailed construction-planning blueprints appraisal and approval  (2)
Obtain Investment Certificate  (3)
Obtain seal and seal registration Certification  (2)
Obtain certificate of tax registration  (2)
Publish in newspaper  (1)
Open bank account  (1)
Obtain approval on environmental impact assessment  (3)
Obtain fire prevention and fighting appraisal and approval (for conceptual design dossier)  (2)
Obtain opinions on conceptual design  (2)
Obtain fire prevention and fighting approval (for construction drawings dossiers)  (2)
Obtain land recovery notice; Request to set up compensation, support and resettlement council  (1)
Obtain approval on instruction for landmarks definition for compensation, support and resettlement  (2)
Make landmarks definition plan  (1)
Receive landmarks on site  (2)
Make detailed plan for compensation, support and resettlement  (1)
Request for land lease  (2)
Making payment upon approved detailed plan for compensation, support and resettlement  (1)
Obtain approval on instruction for landmarks definition for calculating land rental  (2)
Receive the land plot on site  (1)
Determine land rental, land rental rate  (4)
Sign land lease contract  (2)
Declare and pay land rental  (1)
Obtain extract of land plot location  (2)
Obtain land use right, house and land-attached asset ownership certificate  (3)

Preview & Print

Properties
 
58
Request determination of land rental, land rental rate

Timeframe ( ver detalles )

Espera hasta paso siguiente

15 mn  -  3h 30 mn
8 days  -  35 days

Contact details

Entity in charge

Hanoi Authority for Finance

38B Hai Ba Trung Street, Hoan Kiem District , Hanoi
Tel: +84 4 3938 6565
Website: http://www.sotaichinh.hanoi.gov.vn/

Unit in charge

Reception and Release Desk

Tue: 08:00-11:30
Wed: 08:00-11:30
Thu: 08:00-11:30
Fri: 08:00-11:30

Person in charge

Mr. Nguyen Manh Hung

Tel: +84 4 3938 6565

Expected results

Receipt of application file (Finance) 01 - Receipt of application file (Finance)

Requirements

For annual payment (defining land rental rate of the first period)
1.
Request letter for defining land rental rate (original)
of the investor (company) signed by the legal representative and sealed by the company
2. 01 - Libre deuda de patente
Decision on land lease (an authentic copy)
of Hanoi People’s Committee (certified by the company)
3. Investment certificate (H2)
Investment certificate (H2) (an authentic copy)
(certified by the company)
4.
Approved 1/500-scale detailed construction blueprint (an authentic copy)
or Master plan and preliminary architectural plan approval
Master plan and preliminary architectural plan approval (an authentic copy)
scale 1/500 of the land plot (certified by the company)
5. 01 - Libre deuda de patente
Current condition land map (an authentic copy)
6. Written opinions on conceptual design
Written opinions on conceptual design (an authentic copy)
of relevant competent agency (if any)
7.
Payment receipt of land rental and other related financial obligations (an authentic copy)
of the land plot in previous period (if any)
8. Land handing over minutes
Land handing over minutes (an authentic copy)
on site after completing land clearance of Hanoi Natural Resources & Environment Department (certified by the company)
9. 01 - Libre deuda de patente
Passport or ID card (original)
of the person submitting the application file
10. Power of attorney (2)
Power of attorney (2) (original)
of the company signed by the legal representative and sealed by the company to the person submitting the application file if the legal representative does not submit the application file directly
For land plot valued at VND 15 billions or more (based on the price regulated by Hanoi's People Commitee), supplement the following:
1.
Statistics and commitment document on construction area (an authentic copy)

Time frame

Waiting time in queue: Min.  5mn - Max. 3h
Attention at counter: Min.  10mn - Max.  30mn
Waiting time until next step: Min.  8 days - Max.  35 days

Legal justification

1. Law on Land No. 13/2003/QH11
Law on Land No. 13/2003/QH11
Article 108
2. Decree No. 181/2004/ND-CP of the Government dated October 29, 2004 on implementation of the Land Law
Decree No. 181/2004/ND-CP of the Government dated October 29, 2004 on implementation of the Land Law
3. Decree No. 142/ 2004/ND-CP of the Government dated November 14, 2005, on the collection of land rents and water surface rents
Decree No. 142/ 2004/ND-CP of the Government dated November 14, 2005, on the collection of land rents and water surface rents
4. Decree No. 121/2010/ND-CP of the Government dated December 30, 2010, amending and supplementing a number of articles of the Government's Decree No. 142/ 2004/ND-CP of November 14, 2005, on the collection of land rents and water surface rents
Decree No. 121/2010/ND-CP of the Government dated December 30, 2010, amending and supplementing a number of articles of the Government's Decree No. 142/ 2004/ND-CP of November 14, 2005, on the collection of land rents and water surface rents
5. Circular No. 120/2005/TT-BTC of the Ministry of Finance dated Dec 30, 2005 guiding the implementation of the Government’s Decree No. 142/2005/ND-CP of November 14, 2005, on collection of land rents and water surface rents
Circular No. 120/2005/TT-BTC of the Ministry of Finance dated Dec 30, 2005 guiding the implementation of the Government’s Decree No. 142/2005/ND-CP of November 14, 2005, on collection of land rents and water surface rents
6. Circular No. 141/2007/TT-BTC of the Ministry of Finance dated November 30, 2007, guiding amendments and supplements to Circular No. 120/2005/TT-BTC of December 30, 2005, on collection of land rents and water surface rents
Circular No. 141/2007/TT-BTC of the Ministry of Finance dated November 30, 2007, guiding amendments and supplements to Circular No. 120/2005/TT-BTC of December 30, 2005, on collection of land rents and water surface rents
7. Circular No. 94/2011/TT-BTC of the Ministry of Finance dated June 29, 2011, amending and supplementing the Finance Ministry’s Circular No. 120/2005/TT-BTC of December 30, 2005, guiding the Government’s Decree No. 142/2005/ND-CP dated November 14, 2005, on collection of land rent
Circular No. 94/2011/TT-BTC of the Ministry of Finance dated June 29, 2011, amending and supplementing the Finance Ministry’s Circular No. 120/2005/TT-BTC of December 30, 2005, guiding the Government’s Decree No. 142/2005/ND-CP dated November 14, 2005, on collection of land rent
8. Decree No. 198/2004/ND-CP of the Government dated December 3, 2004, on land use levy collection
Decree No. 198/2004/ND-CP of the Government dated December 3, 2004, on land use levy collection
9. Decree No. 84/2007/ND-CP of the Government dated May 25, 2007 with additional provisions on issuance of land use right certificates; on land recovery; on exercise of land use rights;
Decree No. 84/2007/ND-CP of the Government dated May 25, 2007 with additional provisions on issuance of land use right certificates; on land recovery; on exercise of land use rights;
10. Decree No. 120/2010/ND-CP of the Government dated December 30, 2010, amending and supplementing a number of articles of the Government's Decree No. 198/ 2004/ND-CP of December 03, 2004, on the collection of land use levy
Decree No. 120/2010/ND-CP of the Government dated December 30, 2010, amending and supplementing a number of articles of the Government's Decree No. 198/ 2004/ND-CP of December 03, 2004, on the collection of land use levy
11. Circular No. 117/2004/TT-BTC of the Ministry of Finance dated December 7, 2004, guiding the implementation of the Government’s Decree No. 198/2004/ND-CP of December 3, 2004, on land use levy collection
Circular No. 117/2004/TT-BTC of the Ministry of Finance dated December 7, 2004, guiding the implementation of the Government’s Decree No. 198/2004/ND-CP of December 3, 2004, on land use levy collection
12. Circular No. 93/2011/TT-BTC of the Ministry of Finance dated June 29, 2011, amending and supplementing Circular No. 117/2004/TT-BTC dated December 7, 2004, guiding the implementation of the Government’s Decree No. 198/2004/ND-CP dated December 3, 2004, on land use levy collection
Circular No. 93/2011/TT-BTC of the Ministry of Finance dated June 29, 2011, amending and supplementing Circular No. 117/2004/TT-BTC dated December 7, 2004, guiding the implementation of the Government’s Decree No. 198/2004/ND-CP dated December 3, 2004, on land use levy collection
13. Decree No. 69/2009/ND-CP of the Government dated dated August 13, 2009, additionally providing for land use planning, land prices, land recovery, compensation, support and resettlement
Decree No. 69/2009/ND-CP of the Government dated dated August 13, 2009, additionally providing for land use planning, land prices, land recovery, compensation, support and resettlement
14. Decision No. 09/2012/QĐ-UBND of Hanoi People's Committee dated May 21, 2012, on the management of investment and construction of projects of investment in Hanoi
Decision No. 09/2012/QĐ-UBND of Hanoi People's Committee dated May 21, 2012, on the management of investment and construction of projects of investment in Hanoi
15. Decision No. 02/2010/QD-UBND
Decision No. 02/2010/QD-UBND
16. Decision 48/2011/QD-UBND
Decision 48/2011/QD-UBND
17. Decision 10/2012/QD-UBND
Decision 10/2012/QD-UBND
18. Decision 15/2012/QD-UBND
Decision 15/2012/QD-UBND

Additional information

Land evaluation process
Certification Finance Certification Finance

Recourse: Hanoi Authority for Finance

Entity in charge

Hanoi Authority for Finance

38B Hai Ba Trung Street, Hoan Kiem District , Hanoi
Tel: +84 4 3938 6565
Website: http://www.sotaichinh.hanoi.gov.vn/

Unit in charge

Reception and Release Desk

Tue: 08:00-11:30
Wed: 08:00-11:30
Thu: 08:00-11:30
Fri: 08:00-11:30

Person in charge

Mr. Le Anh Tai

Head of Unit
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License