List of steps
(Total number of steps: 69)
Meet HAPI
Legalize foreign documents  (3)
Translate foreign documents  (2)
Define location  (1)
Propose to supplement investment project to the list of investment projects  (1)
Request to be appointed as investor of investment project  (2)
Obtain current condition land map  (1)
Prepare construction dossier (including: fire fighting design dossier)  (1)
Obtain agreement on location plan  (2)
Define red line boundaries and technical infrastructure indications  (3)
Obtain construction planning certificate (or planning information)  (2)
Obtain planning license  (2)
Obtain master plan and and preliminary architectural plan approval  (2)
Obtain 1/500-scale detailed construction-planning tasks appraisal and approval  (2)
Obtain 1/500-scale detailed construction-planning blueprints appraisal and approval  (2)
Obtain Investment Certificate  (3)
Obtain seal and seal registration Certification  (2)
Obtain certificate of tax registration  (2)
Publish in newspaper  (1)
Open bank account  (1)
Obtain approval on environmental impact assessment  (3)
Obtain fire prevention and fighting appraisal and approval (for conceptual design dossier)  (2)
Obtain opinions on conceptual design  (2)
Obtain fire prevention and fighting approval (for construction drawings dossiers)  (2)
Obtain land recovery notice; Request to set up compensation, support and resettlement council  (1)
Obtain approval on instruction for landmarks definition for compensation, support and resettlement  (2)
Make landmarks definition plan  (1)
Receive landmarks on site  (2)
Make detailed plan for compensation, support and resettlement  (1)
Request for land lease  (2)
Making payment upon approved detailed plan for compensation, support and resettlement  (1)
Obtain approval on instruction for landmarks definition for calculating land rental  (2)
Receive the land plot on site  (1)
Determine land rental, land rental rate  (4)
Sign land lease contract  (2)
Declare and pay land rental  (1)
Obtain extract of land plot location  (2)
Obtain land use right, house and land-attached asset ownership certificate  (3)

Preview & Print

Properties
 
62
Submit application for land lease contract

Timeframe ( ver detalles )

Espera hasta paso siguiente

10 mn  -  1h 30 mn
0 days  -  7 days

Contact details

Entity in charge

Hanoi Natural Resources & Environment Department

18 Huynh Thuc Khang Street - Dong Da District , Hanoi
Tel: + 84 4 3773 1566
Fax: +84 4 3773 1566
Website: http://tnmtnd.hanoi.gov.vn/

Unit in charge

Reception & Release Desk (DONRE)

Mon: 08:00-12:00, 13:00-17:00
Tue: 08:00-12:00, 13:00-17:00
Wed: 08:00-12:00, 13:00-17:00
Thu: 08:00-12:00, 13:00-17:00
Fri: 08:00-12:00, 13:00-17:00
Sat: 08:00-12:00

Person in charge

Ms. Pham Thi Hai Yen

Executive
Tel: + 84 4 3773 1563

Expected results

Receipt of application file (N5) 01 - Receipt of application file (N5)

Requirements

1. 01 - Libre deuda de patente
Official letter on land rental, land rental rate (original)
2. 01 - Libre deuda de patente
Passport or ID card
of the person submitting the application file
3. 01 - Libre deuda de patente
Letter of introduction (original)
of the company signed by the legal representative and sealed by the company to the person submitting the application file if the legal representative does not submit the application file directly

Time frame

Waiting time in queue: Min.  5mn - Max. 1h
Attention at counter: Min.  5mn - Max.  30mn
Waiting time until next step: Max.  7 days

Legal justification

1. Law on Land No. 13/2003/QH11
Law on Land No. 13/2003/QH11
Article 122.3
2. Circular No. 09/2007/TT-BTNMT of the Ministry of Natural Resources and Environment dated August 02, 2007 guiding the compilation, revision and management of cadastral dossiers
Circular No. 09/2007/TT-BTNMT of the Ministry of Natural Resources and Environment dated August 02, 2007 guiding the compilation, revision and management of cadastral dossiers
Section II.3
3. Decision No. 02/2010/QD-UBND
Decision No. 02/2010/QD-UBND
Article 21
4. Decision 1611/QD-UBND
Decision 1611/QD-UBND
Section II.I.1

Additional information

Within 03 working days as from the date of receiving documents, Hanoi Natural Resources & Environment Department shall compose draft of land lease contract and send to the company. The company shall sign and send back the land lease contract to Hanoi Natural Resources & Environment Department, if they agree with the draft. The company shall collect the land lease contract signed by Hanoi Natural Resources & Environment Department after 07 working days as from the date of submitting documents (not including duration that the company consider and sign the contract).
Certification Land Certification Land

Recourse: Hanoi Natural Resources & Environment Department

Entity in charge

Hanoi Natural Resources & Environment Department

18 Huynh Thuc Khang Street - Dong Da District , Hanoi
Tel: + 84 4 3773 1566
Fax: +84 4 3773 1566
Website: http://tnmtnd.hanoi.gov.vn/

Unit in charge

Reception Unit

Mon: 08:00-12:00, 13:00-17:00
Tue: 08:00-12:00, 13:00-17:00
Wed: 08:00-12:00, 13:00-17:00
Thu: 08:00-12:00, 13:00-17:00
Fri: 08:00-12:00, 13:00-17:00

Person in charge

Mr. Trinh Que Lam

Executive
Tel: +84 4 3773 5113