Requirements
Legal dossier, including:
1.
Statement for construction design evaluation (original)
in accordance with form in Appendix 3 of Decision 56/2013/QD-UBND
2.
Decision on approval of investment project on the construction of work (Simple copy)
certified by investor (company) for case of two or three-step design
or
In-principle approval on construction of work (original)
certified by investor (company) for case of one-step design
3.
Conceptual design dossier approved together with investment project on construction of work (original)
4.
Consolidated report of investor (company) (original)
on contents as provided for under Article 20.1.a,b of Decree 15/2013/ND-CP
5.
Design explanation (original)
(in compliance with Article 7.4 Circular 13/2013/TT-BXD)
6.
Business registration certificate (an authentic copy)
of design consulting company
7.
Practicing certificate (an authentic copy)
of leaders of sections of electricity, water, structure, architecture
Drawing dossier: technical design drawings and construction drawings must satisfy following requirements:
1.
Land plot layout in the IZ (original)
2.
Master plan drawings (original)
3.
Construction of work items' plan, vertical, section drawings (original)
4.
Design drawings on construction method (original)
5.
Drawings on construction structure (original)
6.
Drawings on technical infrastructure works (original)
Time frame
Time limit for handling the application file: 20 working days for one-step design project and 30 working days for two or three-step design project as from the date of submitting application file.
Waiting time in queue:
Max. 10mn
Attention at counter:
Min. 5mn - Max. 30mn
Waiting time until next step:
Min. 20 days - Max. 30 days
Legal justification
1.
Law No. 50/2014/QD13 dated 18/06/2014 of the National Assembly on Construction
2.
Decree No. 59/2015/ND-CP of the Government dated June 18, 2015 on construction investment project management
3.
Circular No. 18/2016/TT-BXD dated June 30, 2016 of the Ministry of Construction on detailing and guiding some contents on project appraisal and approval and design and estimate of works construction
4.
Decision No. 56/2013/QD-UBND of Hanoi People's Committee dated Dec 11, 2103 prescribing verification, appraisal and approval for works construction design in Hanoi
articles 9, 10, 11
5.
Decree No. 164/2013/ND-CP of the Government dated November 12, 2013 amending and supplementing a number of Articles of the Government’s Decree No. 29/2008/ND-CP dated March 14, 2008, providing for industrial parks, export processing zones and economic zones
Article 1.21
6.
Circular No. 19/2009/TT- BXD of the Ministry of Construction dated June 30, 2009 stipulating the state management of investment and construction in industrial parks and economic zones
Article 2
7.
Decision No. 63/2009/QD-UBND of Hanoi People's Committee dated April 27, 2009 on functions, duties and authorities of HIZA
Article 2
Additional information
Number of application file: 1 legal dossier and 4 drawing dossier.
Works subject to construction design evaluation is stipulated in Article 21.1 of Decree No. 15/2013/ND-CP of the Government.
Grade of construction works to define works subject to construction design evaluation carried by State management authority on construction is stipulated in Appendix 1 of Circular No. 10/2013/TT-BXD of the Ministry of Construction.
HIZA has authority to evaluate design of Grade III and IV construction works in industrial zones, export processing zones and hi-tech parks in Hanoi.
We only describe here case of construction design evaluation of works subject to HIZA’s authority.