Invalid column name 'oldid'.
List of steps
(Total number of steps: 44)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Sign MOU on land lease  (1)
Declare investment project information online
Obtain Investment Registration Certificate (IRC)  (3)
Obtain authenticated copies of IRC  (2)
Obtain Enterprise Registration Certificate (ERC)  (5)
Make seal and notify seal specimen  (2)
21
Make seal
Open bank account  (1)
Obtain land use right certificate  (2)
Obtain construction planning information  (2)
Obtain 1/500-scale master plan approval  (2)
Obtain fire prevention and fighting appraisal and approval (for conceptual design dossier)  (2)
Obtain approval on environmental impact assessment  (3)
Request for conceptual design evaluation  (2)
Obtain fire prevention and fighting approval  (2)
Request for construction design evaluation  (2)
Obtain authenticated copies of EIA report approval and certificate of fire fighting  (2)
Obtain construction permit  (2)

Preview & Print

Properties
 
32
Prepare EIA report
(last modified: 1/11/2018)

Costs

( ver detalles )

Espera hasta paso siguiente

VND 20000000
30 days  -  45 days

Contact details

Entity in charge

Any authorized EIA report consulting companies


List of some environment consulting companies (not exhaustive) List of some environment consulting companies (not exhaustive)

Expected results

EIA report EIA report

Costs

Cost detail

Hypothesis

VND 20,000,000
Fee for making EIA report for reference only
This cost is depended on size and nature of the project. The cost given here is for reference only.

Time frame

Waiting time until next step: Min. 30 days - Max. 45 days

Legal justification

1. Law No. 52/2005/QH11 of the National Assembly on Environmental Protection
Law No. 52/2005/QH11 of the National Assembly on Environmental Protection
articles 18, 19, 20
2. Decree No. 29/2011/ND-CP of the Government dated April 8, 2011 on strategic environmental assessment, environmental impact assessment and environmental protection commitment
Decree No. 29/2011/ND-CP of the Government dated April 8, 2011 on strategic environmental assessment, environmental impact assessment and environmental protection commitment
articles 12, 13, 14, 15, 16, 17
3. Circular No. 26/2011/TT-BTNMT of the Ministry of Natural Resources and Environment detailing a number of articles of the Government’s Decree No. 29/2011/ND-CP dated April 8, 2011 on strategic environmental assessment, environmental impact assessment and environmental protection commitment
Circular No. 26/2011/TT-BTNMT of the Ministry of Natural Resources and Environment detailing a number of articles of the Government’s Decree No. 29/2011/ND-CP dated April 8, 2011 on strategic environmental assessment, environmental impact assessment and environmental protection commitment
articles 10, 12

Additional information

Projects subject to making of EIA report are listed in Appendix II to Decree 29/2011/ND-CP. EIA report must be appraised and approved by provincial people’s committee, except projects that are appraised and approved by the Ministry of Natural Resources and Environment as listed in Appendix III to Decree 29/2011/ND-CP. For other projects, the company shall have to make and register the written environment protection commitment to the district-level people’s Committee where the project is located.
A company being the owner of an investment project for which an environmental impact assessment (EIA) report must be formulated shall carry out itself, or hire a consultancy organization which satisfies all conditions stipulated in Article 8 of Decree 29/2011/ND-CP to carry out EIA and formulate an EIA report for the project.
We only describe here procedures related to making and requesting for EIA report approval at Hanoi People’s Committee.
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License