List of steps
(Total number of steps: 44)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Sign MOU on land lease  (1)
Declare investment project information online
Obtain Investment Registration Certificate (IRC)  (3)
Obtain authenticated copies of IRC  (2)
Obtain Enterprise Registration Certificate (ERC)  (5)
Make seal and notify seal specimen  (2)
21
Make seal
Open bank account  (1)
Obtain land use right certificate  (2)
Obtain construction planning information  (2)
Obtain 1/500-scale master plan approval  (2)
Obtain fire prevention and fighting appraisal and approval (for conceptual design dossier)  (2)
Obtain approval on environmental impact assessment  (3)
Request for conceptual design evaluation  (2)
Obtain fire prevention and fighting approval  (2)
Request for construction design evaluation  (2)
Obtain authenticated copies of EIA report approval and certificate of fire fighting  (2)
Obtain construction permit  (2)

Preview & Print

Properties
 
30
Submit application for fire prevention and fighting approval (for conceptual design dossier)
(last modified: 1/11/2018)

Timeframe ( ver detalles )

Espera hasta paso siguiente

5 mn  -  30 mn
0 days  -  3 days

Contact details

Entity in charge

Hanoi Fire Fighting and Prevention Police

1, 2 Fl. CT14A2 Building, Nam Thang Long New Town, Lac Long Quan Road, Tay Ho District , Hanoi
Tel: +84 4 3939 7981

Unit in charge

Reception & Release Desk (Fire Prevention Police)

Mon: 08:00-12:00, 13:00-17:00
Tue: 08:00-12:00, 13:00-17:00
Wed: 08:00-12:00, 13:00-17:00
Thu: 08:00-12:00, 13:00-17:00
Fri: 08:00-12:00, 13:00-17:00
Sat: 08:00-12:00

Person in charge

Mr. Tran Tuan Dung

Officer
Tel: +84 936 468 789

Expected results

Receipt of application file for fire prevention 01 - Receipt of application file for fire prevention

Requirements

Representatives
1. Written request for opinions on the fire prevention and fighting solutions
Written request for opinions on the fire prevention and fighting solutions (original)
2. Investment certificate (H2)
Investment certificate (H2) (Simple copy)
certified true copy by company
3. 01 - Libre deuda de patente
Cost estimation of total investment capital of project, building works (Simple copy)
certified by company (investor)
4. 01 - Libre deuda de patente
Drawings and explanations of conceptual design (Simple copy)
certified by company (investor) demonstrating the requirements for fire prevention and fighting solutions prescribed in Clause 1, 2, 3, 4, 5 and 6 Article 13 of Decree 79/2014/ND-CP
For case of authorization
1. Power of attorney (2)
Power of attorney (2) (original)
given by the company to the other person or company submitting application file

Time frame

Time limits for fire prevention and fighting design appraisal and approval calculated from fully submitting the valid dossier for conceptual design are as follows:
- Within 10 working days for projects of Group A;
- Within 5 working days for projects of Group B and Group C;
The classification of projects and constructions to Group A, B, C shall be carried out under the Government’s provisions on construction investment project management.
Waiting time in queue: Max. 15mn
Attention at counter: Min. 5mn - Max. 15mn
Waiting time until next step: Max. 3 days

Legal justification

1. Law No. 27/2001/QH10 on Fire prevention and Fighting of National Assembly (as amended by Law No. 40/2013/QH13)
Law No. 27/2001/QH10 on Fire prevention and Fighting of National Assembly (as amended by Law No. 40/2013/QH13)
Article 15
2. Decree No. 79/2014/ND-CP of the Government dated Jul 31, 2014 detailing the implementation of a number of articles of the Law on fire prevention and fighting and Law on amendment of a number of articles of the Law on fire prevention and fighting
Decree No. 79/2014/ND-CP of the Government dated Jul 31, 2014 detailing the implementation of a number of articles of the Law on fire prevention and fighting and Law on amendment of a number of articles of the Law on fire prevention and fighting
articles 13, 15
3. Circular No. 66/2014/TT-BCA
Circular No. 66/2014/TT-BCA
Article 7

Additional information

Number of application file: 2 sets. The application file must be certified by investors and translated the explanations into Vietnamese if they are in foreign language.
Project and works prescribed in Appendix IV to Decree No. 79/2014/ND-CP, when being newly constructed, renovated or utility-related changed, must be appraised and approved in term of fire prevention and fighting design by fire prevention and fighting police agencies.
Based on the nature and scale of project or construction works, fire prevention and fighting police agencies may either fire prevention and fighting police department of Ministry of Public Security or fire prevention and fighting police department of Hanoi People's Committee. We only describe here case that the appraisal and approval of fire prevention and fighting design is made by fighting police department of Hanoi People's Committee.
Fire prevention and fighting police department shall make the written recommendation on the fire prevention and fighting solutions for conceptual design dossier.

Recourse: Hanoi Fire Fighting and Prevention Police

Entity in charge

Hanoi Fire Fighting and Prevention Police

1, 2 Fl. CT14A2 Building, Nam Thang Long New Town, Lac Long Quan Road, Tay Ho District , Hanoi
Tel: +84 4 3939 7981

Unit in charge

Fire Prevention Guide Division

Mon: 08:00-12:00, 13:00-17:00
Tue: 08:00-12:00, 13:00-17:00
Wed: 08:00-12:00, 13:00-17:00
Thu: 08:00-12:00, 13:00-17:00
Fri: 08:00-12:00, 13:00-17:00
Sat: 08:00-12:00

Person in charge

Mr. Vu Duc Hung

Head of fire prevention appraisal guide and checking team
Tel: + 84 912 591 916
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License