Requirements
Legal dossier, including:
1.
Statement for obtaining opinion on conceptual design (original)
2.
Signed land lease contract (Simple copy)
certified by company
or
Land use right certificate (Simple copy)
certified by company
3.
Investment Certificate (Simple copy)
4.
Investment project on the construction of works explanation (original)
made in accordance with Article 7, Decree 12/2009/ND-CP
5.
Conceptual design dossier (original)
6.
Construction survey dossier relating to design drawings and explanations (original)
7.
Business registration certificate (an authentic copy)
8.
Practicing certificate (an authentic copy)
9.
Written consideration and recommendation on fire prevention and fighting solutions (an authentic copy)
Drawing dossier made in accordance with Article 8, Decree 12/2009/ND-CP to satisfy following requirements:
1.
Land plot layout in the IZ (original)
2.
Master plan drawings (original)
3.
Drawings on architectural plan (original)
4.
Drawings on major structure plan (original)
5.
Drawings on technical infrastructure works (original)
Time frame
Time limit for handling the application file: 15 working days for Group B project and 10 working days for Group C project as from the date of submitting application file.
Waiting time in queue:
Max. 10mn
Attention at counter:
Min. 5mn - Max. 30mn
Waiting time until next step:
Min. 10 days - Max. 15 days
Legal justification
1.
Law No. 50/2014/QD13 dated 18/06/2014 of the National Assembly on Construction
2.
Decree No. 59/2015/ND-CP of the Government dated June 18, 2015 on construction investment project management
3.
Circular No. 18/2016/TT-BXD dated June 30, 2016 of the Ministry of Construction on detailing and guiding some contents on project appraisal and approval and design and estimate of works construction
4.
Decree No. 164/2013/ND-CP of the Government dated November 12, 2013 amending and supplementing a number of Articles of the Government’s Decree No. 29/2008/ND-CP dated March 14, 2008, providing for industrial parks, export processing zones and economic zones
Article 1.21
5.
Circular No. 19/2009/TT- BXD of the Ministry of Construction dated June 30, 2009 stipulating the state management of investment and construction in industrial parks and economic zones
Article 2
6.
Decision No. 63/2009/QD-UBND of Hanoi People's Committee dated April 27, 2009 on functions, duties and authorities of HIZA
Article 2
7.
Decision No. 56/2013/QD-UBND of Hanoi People's Committee dated Dec 11, 2103 prescribing verification, appraisal and approval for works construction design in Hanoi
articles 6, 7
Additional information
Number of application file: 1 set of legal dossier and 1 set of drawing dossier.
Formality of documents must comply with Article 14.3, 14.4 of Circular No. 10/2013/TT-BXD of the Ministry of Construction.
Obtaining opinions on conceptual design is applied to project having total investment capital of VND 15 billion or more, excluding land use levies.
HIZA has authority to provide opinions on conceptual design of investment project on construction of works, public service house, employee house of Group B and C (having total investment capital of VND 15 billions or more, excluding land use levies) in industrial zones, export processing zones, hi-tech parks in Hanoi.
We only describe here case that providing opinions on conceptual design is of HIZA’s authority.