List of steps
(Total number of steps: 44)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Sign MOU on land lease  (1)
Declare investment project information online
Obtain Investment Registration Certificate (IRC)  (3)
Obtain authenticated copies of IRC  (2)
Obtain Enterprise Registration Certificate (ERC)  (5)
Make seal and notify seal specimen  (2)
21
Make seal
Open bank account  (1)
Obtain land use right certificate  (2)
Obtain construction planning information  (2)
Obtain 1/500-scale master plan approval  (2)
Obtain fire prevention and fighting appraisal and approval (for conceptual design dossier)  (2)
Obtain approval on environmental impact assessment  (3)
Request for conceptual design evaluation  (2)
Obtain fire prevention and fighting approval  (2)
Request for construction design evaluation  (2)
Obtain authenticated copies of EIA report approval and certificate of fire fighting  (2)
Obtain construction permit  (2)

Preview & Print

Properties
 
12
Verify the status of the application
(last modified: 1/11/2018)

Timeframe ( ver detalles )

Espera hasta paso siguiente

10 mn  -  45 mn
0 days  -  12 days

Contact details

Entity in charge

Hanoi Industrial and Export Processing Zones Authority (HIZA)

7-storey Building, CC02, Mo Lao Urban Area, Mo Lao Ward, Ha Dong , Hanoi
Tel: +84 4 3356 0426
Fax: +84 4 3356 0460
Email: vanthu_bqlkcncx@hanoi.gov.vn
Website: http://hiza.gov.vn

Unit in charge

Reception & Release Desk (HIZA)

Mon: 08:00-12:00, 13:00-17:00
Tue: 08:00-12:00, 13:00-17:00
Wed: 08:00-12:00, 13:00-17:00
Thu: 08:00-12:00, 13:00-17:00
Fri: 08:00-12:00, 13:00-17:00

Person in charge

Mr. Pham Duc Hung, Mr. Vu Thanh Tung

Office Staff
Tel: +84 4 3356 0426
Email: phamduchung_bqlkcncx@hanoi.gov.vn

Expected results

Result notification (Viet) 01 - Result notification (Viet)

Time frame

Waiting time in queue: Min. 5mn - Max. 30mn
Attention at counter: Min. 5mn - Max. 15mn
Waiting time until next step: Max. 12 days

Additional information

The investor is requested to contact Reception & Release Desk after 3 working days as from submission of application file to receive the information of application file validity or receive requirement of supplementation or explanation.

When the investor re-submits its application, HAPI may either (i) withdraw the original receipt of application and issue a new one or (ii) indicate in the original receipt the additional documents being submitted. The maximum time defined by law for issuance of the Investment Certificate will be recounted from the date of submission of the additional documents.

Recourse: Hanoi Authority for Planning & Investment (HAPI)

Entity in charge

Hanoi Authority for Planning & Investment (HAPI)

16 Cat Linh Street, Dong Da District , Hanoi
Tel: +84 43 825 6637
Email: sokhdthanoi@hapi.gov.vn
Website: http://www.hapi.gov.vn

Unit in charge

Administration Office

Mon: 08:00-12:00, 13:00-17:00
Tue: 08:00-12:00, 13:00-17:00
Wed: 08:00-12:00, 13:00-17:00
Thu: 08:00-12:00, 13:00-17:00
Fri: 08:00-12:00, 13:00-17:00

Person in charge

Mr. Nguyen Huu Luong

Deputy Office Manager
Tel: + 84 43 825 6637
Email: luongnh@hapi.gov.vn
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License