Requirements
Representatives
1.
Request for fire prevention and fighting appraisal and approval (original)
2.
Drawings and explanations of technical design or design drawings for execution (Simple copy)
certified by company (investor) demonstrating the requirements for fire prevention and fighting solutions prescribed in Clause 1, 2, 3, 4, 5 and 6 Article 13 of Decree No. 79/2014/ND-CP
3.
Cost estimation of total investment capital of project, building works (Simple copy)
certified by company (investor)
4.
Written approval on planning of competent authorities (Simple copy)
certified true copy by company
For case of authorization
1.
Power of attorney (2) (original)
given by the company to the other person or company submitting application file
Time frame
For technical design and construction drawings for execution, the time limits for fire prevention and fighting design appraisal and approval calculated from fully submitting the valid dossier are as follows:
- Within 15 working days for projects and constructions of Group A;
- Within 10 working days for projects and constructions of Group B and Group C.
The classification of projects and constructions to Group A, B, C shall be carried out under the Government’s provisions on construction investment project management.
Waiting time in queue:
Max. 15mn
Attention at counter:
Min. 5mn - Max. 15mn
Waiting time until next step:
Max. 3 days
Legal justification
1.
Law No. 27/2001/QH10 on Fire prevention and Fighting of National Assembly (as amended by Law No. 40/2013/QH13)
Article 15
2.
Decree No. 79/2014/ND-CP of the Government dated Jul 31, 2014 detailing the implementation of a number of articles of the Law on fire prevention and fighting and Law on amendment of a number of articles of the Law on fire prevention and fighting
articles 13, 15
3.
Circular No. 66/2014/TT-BCA
Article 7
Additional information
Number of application file: 2 sets. The application file must be certified by investors and translated the explanations into Vietnamese if they are in foreign language.
Project and works prescribed in Appendix IV to Decree No. 79/2014/ND-CP, when being newly constructed, renovated or utility-related changed, must be appraised and approved in term of fire prevention and fighting design by fire prevention and fighting police agencies.
Based on the nature and scale of project or construction works, fire prevention and fighting police agencies may either fire prevention and fighting police department of Ministry of Public Security or fire prevention and fighting police department of Hanoi People's Committee. We only describe here case that the appraisal and approval of fire prevention and fighting design is made by fighting police department of Hanoi People's Committee.
Fire prevention and fighting police department shall issue certificate of fire prevention and fighting for technical design or design drawings for execution dossiers.