Invalid column name 'oldid'.
List of steps
(Total number of steps: 46)
Meet HHTP MB
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Obtain written notification on appraisal of satisfying investment conditions  (2)
Define location plan for project using land  (2)
Obtain Investment Registration Certificate (IRC)  (2)
Obtain authenticated copies of Investment Certificate  (2)
Obtain certificate of tax registration  (2)
Open bank account  (1)
Publish in newspaper  (1)
Obtain approval on environmental impact assessment  (3)
Obtain construction planning certificate or planning license  (2)
Obtain 1/500-scale detailed construction-planning tasks approval  (2)
Obtain 1/500-scale detailed construction-planning blueprints approval  (2)
Obtain fire prevention and fighting appraisal and approval (for conceptual design dossier)  (2)
Obtain approval on conceptual design  (2)
Obtain current condition land map  (1)
Request for land lease  (5)
Obtain land use right certificate  (2)
Obtain fire prevention and fighting approval  (2)
Obtain construction permit  (2)

Preview & Print

Properties
 
Verify status of application file
(last modified: 11/26/2016)
This step is optional

Timeframe ( ver detalles )

Espera hasta paso siguiente

5 mn  -  30 mn
40 days  -  55 days

Contact details

Entity in charge

Hanoi Natural Resources & Environment Department

18 Huynh Thuc Khang Street - Dong Da District , Hanoi
Tel: + 84 4 3773 1566
Fax: +84 4 3773 1566
Website: http://tnmtnd.hanoi.gov.vn/

Unit in charge

Reception & Release Desk (DONRE)

Mon: 08:00-12:00, 13:00-17:00
Tue: 08:00-12:00, 13:00-17:00
Wed: 08:00-12:00, 13:00-17:00
Thu: 08:00-12:00, 13:00-17:00
Fri: 08:00-12:00, 13:00-17:00
Sat: 08:00-12:00

Person in charge

Ms. Nguy Minh Chau

Executive
Tel: +84 4 3773 1563

Expected results

Notification of EIA report supplementation 01 - Notification of EIA report supplementation

Time frame

If the dossier is incomplete or invalid, within five (5) working days, it shall notify in writing the project owner to complete the dossier
The time limit for appraising EIA reports is thirty (30) working days after receiving complete and valid dossiers, and forty-five (45) working days, for projects with complicated environmental impacts. The time limit for approving an EIA report is fifteen (15) working days after receiving a complete and valid dossier. The time limit for appraisal and approval of an EIA report does not include the time for the project owner to finalize the environmental impact assessment report dossier in accordance with conclusion of appraisal council of EIA report.
Without notification, the company will collect the approval on EIA report on date specified in the receipt of application file.
Waiting time in queue: Max. 15mn
Attention at counter: Min. 5mn - Max. 15mn
Waiting time until next step: Min. 40 days - Max. 55 days

Recourse: Hanoi Natural Resources & Environment Department

Entity in charge

Hanoi Natural Resources & Environment Department

18 Huynh Thuc Khang Street - Dong Da District , Hanoi
Tel: + 84 4 3773 1566
Fax: +84 4 3773 1566
Website: http://tnmtnd.hanoi.gov.vn/

Unit in charge

Reception Unit

Mon: 08:00-12:00, 13:00-17:00
Tue: 08:00-12:00, 13:00-17:00
Wed: 08:00-12:00, 13:00-17:00
Thu: 08:00-12:00, 13:00-17:00
Fri: 08:00-12:00, 13:00-17:00

Person in charge

Mr. Trinh Que Lam

Executive
Tel: +84 4 3773 5113
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License