List of steps
(Total number of steps: 42)
Meet HHTP MB
Obtain written notification on appraisal of satisfying investment conditions  (2)
Define location plan for project using land  (2)
Legalize foreign documents  (3)
Translate foreign documents  (2)
Obtain Investment Registration Certificate (IRC)  (2)
Obtain tax registration Certificate  (2)
Open bank account  (1)
Publish in newspaper  (1)
Obtain approval on environmental impact assessment  (3)
Obtain construction planning certificate or planning license  (2)
Prepare construction dossier (including: fire fighting design dossier)  (1)
Obtain 1/500-scale detailed construction-planning tasks approval  (2)
Obtain 1/500-scale detailed construction-planning blueprints approval  (2)
Obtain fire prevention and fighting appraisal and approval (for conceptual design dossier)  (2)
Obtain approval on conceptual design  (2)
Obtain fire prevention and fighting approval (for construction drawings dossiers)  (2)
Obtain current condition land map  (1)
Request for land lease  (5)
Declare and pay land rental  (1)
Obtain land use right certificate  (2)
Obtain construction permit  (2)

Preview & Print

Properties
 
36
Receive landmarks and land plot on site
(last modified: 09/12/2014)

Contact details

Entity in charge

Hoa Lac Hi-Tech Park Management Board (HHTP MB)

Km 29, Thang Long Freeway, Thach That Dist. , Ha Noi
Tel: +84 46 326 9295 /+84 46 326 9294
Email: [email protected]
Website: http://www.hhtp.gov.vn

Unit in charge

Planning, Construction and Environment Department

Mon: 08:00-12:00, 13:00-17:00
Tue: 08:00-12:00, 13:00-17:00
Wed: 08:00-12:00, 13:00-17:00
Thu: 08:00-12:00, 13:00-17:00
Fri: 08:00-12:00, 13:00-17:00

Person in charge

Ms. Tran Ngoc Ha

Deputy Director
Tel: +84 4 6326 9294

Expected results

Landmarks handling over minutes Landmarks handling over minutes
Land plot handing over minutes Land plot handing over minutes

Additional information

The investor shall be invited to receive land mark and land plot on site and sign landmarks and land plot handing over minutes.

Recourse: Hoa Lac Hi-Tech Park Management Board (HHTP MB)

Entity in charge

Hoa Lac Hi-Tech Park Management Board (HHTP MB)

Km 29, Thang Long Freeway, Thach That Dist. , Ha Noi
Tel: +84 46 326 9295 /+84 46 326 9294
Email: [email protected]
Website: http://www.hhtp.gov.vn

Unit in charge

Planning, Construction and Environment Department

Mon: 08:00-12:00, 13:00-17:00
Tue: 08:00-12:00, 13:00-17:00
Wed: 08:00-12:00, 13:00-17:00
Thu: 08:00-12:00, 13:00-17:00
Fri: 08:00-12:00, 13:00-17:00

Person in charge

Mr. Nguyen The Hung - Director

Tel: +84 4 6326 9294
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License