List of steps
(Total number of steps: 42)
Meet HHTP MB
Obtain written notification on appraisal of satisfying investment conditions  (2)
Define location plan for project using land  (2)
Legalize foreign documents  (3)
Translate foreign documents  (2)
Obtain Investment Registration Certificate (IRC)  (2)
Obtain tax registration Certificate  (2)
Open bank account  (1)
Publish in newspaper  (1)
Obtain approval on environmental impact assessment  (3)
Obtain construction planning certificate or planning license  (2)
Prepare construction dossier (including: fire fighting design dossier)  (1)
Obtain 1/500-scale detailed construction-planning tasks approval  (2)
Obtain 1/500-scale detailed construction-planning blueprints approval  (2)
Obtain fire prevention and fighting appraisal and approval (for conceptual design dossier)  (2)
Obtain approval on conceptual design  (2)
Obtain fire prevention and fighting approval (for construction drawings dossiers)  (2)
Obtain current condition land map  (1)
Request for land lease  (5)
Declare and pay land rental  (1)
Obtain land use right certificate  (2)
Obtain construction permit  (2)

Preview & Print

Properties
 
33
Submit application for land lease
(last modified: 09/12/2014)

Timeframe ( ver detalles )

Espera hasta paso siguiente

5 mn  -  40 mn
0 days  -  9 days

Contact details

Entity in charge

Hoa Lac Hi-Tech Park Management Board (HHTP MB)

Km 29, Thang Long Freeway, Thach That Dist. , Ha Noi
Tel: +84 46 326 9295 /+84 46 326 9294
Email: [email protected]
Website: http://www.hhtp.gov.vn

Unit in charge

Planning, Construction and Environment Department

Mon: 08:00-12:00, 13:00-17:00
Tue: 08:00-12:00, 13:00-17:00
Wed: 08:00-12:00, 13:00-17:00
Thu: 08:00-12:00, 13:00-17:00
Fri: 08:00-12:00, 13:00-17:00

Person in charge

Ms. Tran Ngoc Ha

Deputy Director
Tel: +84 4 6326 9294

Expected results

Receipt of application file (HHTP9) 01 - Receipt of application file (HHTP9)

Requirements

1. Application for land lease (Form 2.3.b)
Application for land lease (Form 2.3.b) (original)
2. 01 - Libre deuda de patente
Current condition land map (original)
or cadastral map made by authorized mapping company scale 1/500 - 1/200
3.
Investment project on construction of works (original)
approved by investor

Time frame

Waiting time in queue: Max. 10mn
Attention at counter: Min.  5mn - Max.  30mn
Waiting time until next step: Max.  9 days

Legal justification

1. Law No. 45/2013/QH13 dated November 29, 2013 of the National Assembly on Land
Law No. 45/2013/QH13 dated November 29, 2013 of the National Assembly on Land
Article 150
2. Decree No. 43/2014/NĐ-CP dated May 5, 2014 detailing the implementation of a number of articles of the Land on Land
Decree No. 43/2014/ND-CP of the Government dated May 5, 2014 detailing the implementation of a number of articles of the Land on Land
articles 52, 60.4
3. Decision No. 01/QD-CNCHL dated January 02, 2014 on investment procedure in Hoa Lac High Tech Park
Decision No. 01/QD-CNCHL dated January 02, 2014 on investment procedure in Hoa Lac High Tech Park
Article apdx.2.3

Additional information

Number of application file: 02 original sets

Recourse: Hoa Lac Hi-Tech Park Management Board (HHTP MB)

Entity in charge

Hoa Lac Hi-Tech Park Management Board (HHTP MB)

Km 29, Thang Long Freeway, Thach That Dist. , Ha Noi
Tel: +84 46 326 9295 /+84 46 326 9294
Email: [email protected]
Website: http://www.hhtp.gov.vn

Unit in charge

Planning, Construction and Environment Department

Mon: 08:00-12:00, 13:00-17:00
Tue: 08:00-12:00, 13:00-17:00
Wed: 08:00-12:00, 13:00-17:00
Thu: 08:00-12:00, 13:00-17:00
Fri: 08:00-12:00, 13:00-17:00

Person in charge

Mr. Nguyen The Hung - Director

Tel: +84 4 6326 9294
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License