List of steps
(Total number of steps: 42)
Meet HHTP MB
Obtain written notification on appraisal of satisfying investment conditions  (2)
Define location plan for project using land  (2)
Legalize foreign documents  (3)
Translate foreign documents  (2)
Obtain Investment Registration Certificate (IRC)  (2)
Obtain tax registration Certificate  (2)
Open bank account  (1)
Publish in newspaper  (1)
Obtain approval on environmental impact assessment  (3)
Obtain construction planning certificate or planning license  (2)
Prepare construction dossier (including: fire fighting design dossier)  (1)
Obtain 1/500-scale detailed construction-planning tasks approval  (2)
Obtain 1/500-scale detailed construction-planning blueprints approval  (2)
Obtain fire prevention and fighting appraisal and approval (for conceptual design dossier)  (2)
Obtain approval on conceptual design  (2)
Obtain fire prevention and fighting approval (for construction drawings dossiers)  (2)
Obtain current condition land map  (1)
Request for land lease  (5)
Declare and pay land rental  (1)
Obtain land use right certificate  (2)
Obtain construction permit  (2)

Preview & Print

Properties
 
21
Prepare construction dossier (including: fire fighting design dossier)
(last modified: 29/05/2015)

Espera hasta paso siguiente

15 days  -  30 days

Time frame

Waiting time until next step: Min.  15 days - Max.  30 days

Additional information

When investing in the construction of works, investors (companies) shall make, evaluate and decide on investment in the construction of works, except construction, renovation, repair or upgrading works capitalized at under VND 15 billion (excluding land use levies) in compliance with socio-economic development, branch or construction planning
A project content is composed of explanations and a basic design.