Requirements
1.
Letter of introduction (original)
of the company signed by the legal representative and sealed by the company to the person submitting the application file
2.
Written request for obtaining opinion on conceptual design (original)
Legal dossier, including:
1.
Authenticated copy of Investment Certificate
Dossier showing capability of surveying constructor, including:
1.
Business registration certificate (an authentic copy)
of surveying constructor
2.
Practicing certificate (an authentic copy)
of surveying engineer leader
Dossier showing capability of consulting company making investment project on construction of work, including:
1.
Business registration certificate (an authentic copy)
of consulting company making investment project on construction of work
2.
Practicing certificate (an authentic copy)
of designing leaders
Planning dossier scale 1/500 approved by competent authority, including:
1.
Approved 1/500-scale detailed construction blueprint (Simple copy)
certified true copy by investor (company)
or
Master plan and preliminary architectural plan approval (Simple copy)
certified true copy by investor (company)
or
Documents on architectural planning information (Simple copy)
certified true copy by investor (company)
1.
Written consideration and recommendation on fire prevention and fighting solutions (iz) (Simple copy)
certified true copy by investor (company)
2.
Decision on EIA report approval (Simple copy)
certified true copy by investor (company)
or
Environmental protection commitment (Simple copy)
certified true copy by investor (company)
3.
Written agreement on functional State management (Simple copy)
certified true copy by investor (company)
- dyke management (if any)
- security and national defense (if any)
- cultural or monument work protection (if any)
- high voltage grid (if any)
4.
Written agreement on techinical infrastructure connection (Simple copy)
certified true copy by investor (company)
- water supply (if any)
- water discharge (if any)
- power supply (if any)
Surveying and designing dossier, including:
1.
Report on surveying construction of work: geology, route (if any) (original)
2.
Investment project explanation (original)
3.
Conceptual design drawings (original)
4.
Conceptual design explanation (original)
Time frame
By law, time limit for the authority to handle the application file: 20 working days for Group A project, 15 working days for Group B project and 10 working days for Group C project as from the date of receiving complete application file.
Waiting time in queue:
Max. 10mn
Attention at counter:
Min. 5mn - Max. 30mn
Waiting time until next step:
Min. 10 days - Max. 20 days
Legal justification
1.
Law No. 50/2014/QD13 dated 18/06/2014 of the National Assembly on Construction
Article 58.4
2.
Decree No. 12/2009/ND-CP of the Government dated February 12, 2009, on management of investment projects on the construction of works
articles 6, 7, 8, 9, 10, 11, 12, 13
3.
Decree No. 83/2009/ND-CP of the Government dated October 15, 2009, amending and supplementing a number of Articles of the Government's Decree No. 12/2009/ND-CP of February 12, 2009, on management of work construction investment projects
Article 1.2
4.
Circular No. 03/2009/TT- BXD of the Ministry of Construction dated March 26, 2009 detailing a number of provisions of the Government's Decree No. 12/2009/ND-CP dated February 12, 2009 on management of investment projects on the construction of works
Article 2
5.
Decision No. 56/2013/QD-UBND of Hanoi People's Committee dated Dec 11, 2103 prescribing verification, appraisal and approval for works construction design in Hanoi
articles 6, 7
6.
Official Letter No. 3482/BXD-HDXD of the Ministry of Construction dated Dec 30, 2014 on implementation of Law No. 50/2014/QH13 on Construction
Article III.2.c
7.
Official Letter No. 254/BXD-HDXD of the Ministry of Construction dated Dec 30, 2014 guiding some content of design appraisal in accordance with Law No. 50/2014/QH13 on Construction
Article 3
Additional information
In the project evaluation process, the investors shall have to seek opinions of State management agencies on basic designs. The competent State agencies giving opinions, time limit for giving opinions on basic designs are depended on nature, scale of investment projects as stipulated in Article 2 of Circular 03/2009/TT-BXD.
We only describe here case that providing opinions on conceptual design is of Hanoi Construction Department.