Requirements
1.
Application for construction permit (original)
Documents on land use right, including:
1.
Land use right or house and land-attached asset ownership certificates (Simple copy)
certified true copy by investor (company)
2.
Extract of land plot location (Simple copy)
certified true copy by investor (company)
Construction planning dossier (if any), including:
1.
Approved 1/500-scale detailed construction blueprint (Simple copy)
certified true copy by investor (company)
or
Master plan and preliminary architectural plan approval (Simple copy)
certified true copy by investor (company)
Conceptual design document (if any), including:
1.
Conceptual design dossier approved together with investment project on construction of work (original)
2.
Written opinions on conceptual design (Simple copy)
certified true copy by investor (company)
1.
Approved drawings of fire prevention and fire fire fighting system (Simple copy)
(for construction of work subject to fire prevention and fire fighting approval) certified true copy by investor (company)
2.
Design drawings for construction permit (original)
3.
Authenticated copy of Investment Certificate
4.
Decision on approval of investment project on the construction of work (original)
5.
Report on appraising construction designs (original)
1.
Certificate of fire prevention and fighting appraisal and approval (Simple copy)
certified true copy by investor (company)
2.
Environmental protection commitment (Simple copy)
certified true copy by investor (company)
or
Approved report on environmental impact assess (Simple copy)
certified true copy by investor (company)
3.
Written agreement on techinical infrastructure connection (Simple copy)
certified true copy by investor (company)
4.
Power of attorney (2) (original)
given by investor (company) to the individual or organization submitting application file
Time frame
Waiting time in queue:
Max. 10mn
Attention at counter:
Min. 5mn - Max. 30mn
Waiting time until next step:
Max. 20 days
Legal justification
1.
Law No. 50/2014/QD13 dated 18/06/2014 of the National Assembly on Construction
articles 91, 92, 93, 94, 95
2.
Decree No. 64/2012/ND-CP of the Government dated September 04, 2012 on construction permit
articles 5, 8, 9
3.
Decision No. 59/2013/QD-UBND of Hanoi People's Committee dated Dec 19, 2013 providing details of construction permit in Hanoi
articles 3.2, 5
4.
Circular No. 10/2012/TT-BXD of the Ministry of Construction dated December 20, 2012 guiding in detail some contents of Decree No. 64/2012/ND-CP dated September 04, 2012 of the government concerning issuance of Construction permit
Article 5
5.
Official Letter No. 3482/BXD-HDXD of the Ministry of Construction dated Dec 30, 2014 on implementation of Law No. 50/2014/QH13 on Construction
Article VI.